Kilpatrick Avenue Sewer Project
Updated November 13, 2026
The scope of work for this project in its entirety is as follows:
-
N Kilpatrick Av from W Roscoe St to W Addison St
-
N Kilpatrick Av from W Roscoe St to W School St
-
W School St from N Kilpatrick Av to N Keating Av
-
N Kolmar Av from W Roscoe St to W Cornelia Av
-
W Cornelia Av from N Kolmar Av to N Kenton Av
-
N Kilpatrick Av from W Addison St to W Waveland Av
-
W Waveland Av from N Kilpatrick Av to 387’ East
-
W Patterson Av from N Kilpatrick Av to 392’ East
-
W Warwick Av from N Kilpatrick Av to 258’ East
-
W Grace St from N Kilpatrick Av to 267’ West
Traffic/Street Closures:
-
For the public's safety, the intersection of W School St and N Kilpatrick Ave will remain closed until all sewer connections to the new manhole structure are completed.
Schedule: 11/16/26 – 11/20/26:
Crew S03
-
DWM crew will continue installing 24” diameter reinforced concrete pipe (RCP) on W School St from N Kilpatrick Ave to N Keating Ave.
Lead Service Line Replacement (LSLR) Crew:
On N Kilpatrick Av between Roscoe St to School St.
-
LSLR Crew will complete 14 out of 35 locations.
-
Private Drain (PD) Compliance will complete 7 out of 19 locations.
Completed 11/09/26 – 11/13/26:
DWM Sewer Crew S03
-
DWM crew completed installation of catch basins on N Kilpatrick Av between Roscoe St to School St. Started installation of 24” diameter RCP on W School St from Kilpatrick Ave to Keating Ave.
LSLR Crew:
On N Kilpatrick Av between Roscoe St to School St.
-
LSLR: 8 out of 35 locations completed.
-
PD Compliance: 3 out of 19 locations completed.
Mainline Sewer Main Pipe Progress to date: 3,432 of 5,179 linear feet.
St. Louis Avenue Water and Sewer Project
(only a small portion is within the 30th Ward)
Updated November 13, 2026
The scope of work for the sewer project in its entirety is as follows:
-
N Hamlin Ave from W Byron St to 271' south.
-
N St. Louis Ave from W Grace St to W Waveland Ave.
-
W Waveland Ave from N St. Louis Ave to N Central Park Ave.
-
W Waveland Ave from N St. Louis Ave to N Kimball Ave.
-
N Central Park Ave from W Waveland Ave to 263' north.
-
N Drake Ave from W Waveland Ave to 253' north.
-
N Christiana Ave from W Elston Ave to 54' south.
The scope of work for the water project in its entirety is as follows:
-
N. St. Louis Ave from N. Elston Ave to W. Waveland Ave.
Road Closures / Traffic Control:
-
During working hours, no residential parking/through traffic will be allowed on W. Waveland Ave between N. Central Park Ave and N. Drake Ave (No Parking Signs have been posted).
-
During working hours, no residential parking/through traffic will be allowed on N. Central Park Ave between W. Grace St and W. Waveland Ave (No Parking Signs have been posted).
-
Once mainline sewer construction on N. Drake Ave commences, the intersection of N. Drake Ave and W. Waveland Ave will be closed to allow crews to safely install sewer main through the intersection.
Sewer Schedule - 11/16/26 – 11/20/26:
-
DWM scheduled to complete catch basin installation on N. Central Park Ave between W. Grace St and W. Waveland Ave.
-
DWM tentatively scheduled to begin mainline sewer installation on N. Drake Ave between W. Grace St and W. Waveland Ave – No Parking signs are scheduled to be posted along the construction limits early next week.
Water Schedule - 11/16/26 – 11/20/26:
-
No water main work is scheduled – DWM completed the water main project and has demobilized.
Completed - 11/9/26 – 11/13/26:
-
DWM began catch basin installation on N. Central Park Ave between W. Grace St and W. Waveland Ave.
Mainline Sewer Main Pipe Progress TO DATE: 2,151 of 3,003 linear feet = 71.6%
Mainline Water Main Pipe Progress TO DATE: 1,008 of 1,008 linear feet = 100.0%
Sewer Lining Projects on Linder, Luna, and Melrose
Updated October 15, 2026
The Department of Water Management’s private contractor is scheduled to start work on a Sewer Lining Project with an anticipated start date of Wednesday, September 30, 2026. This project will rehabilitate the existing sewer without the conventional digging method. This sewer rehabilitation will minimize, if not eliminate, street cave-ins due to failure in old sewers. In addition, it will bring better drainage to your area and may help alleviate flooding during heavy rain. T
Project Location:
-
N Linder Ave from W Wrightwood Ave to W Fullerton Ave
-
N Luna Ave from W Wrightwood Ave to W Fullerton Ave
-
W Melrose St from N Melvina Ave to N Meade Ave
Work Includes the following:
-
Cleaning and televising of the main sewer.
-
Cleaning and televising of catch basin pipes (drainage pipe from the structures on the curb-side) followed by lining.
-
Catch basin and manholes structures will be lined.
-
The main sewer will be lined, and the reinstatement of house drain services will proceed and must be completed to relieve the drains.
-
The lined sewer will be televised to ensure that the work is done properly.
What to expect:
During workdays, mobilization will start at 6:00 AM. Actual work will begin at 7:00 AM. Work is expected to be completed by 7:00 PM. No Parking signs will be posted in the immediate area of work a day before any scheduled work. Residents are urged to move their vehicles away from the worksite to avoid being towed. It will be necessary to close lanes of these streets to ensure public safety during work hours. Equipment and materials will be on the street during the work. If necessary, detours and alternative bus stops will be posted.
A day prior to the main sewer lining, contractors will provide door hangers to inform residents of the work. During the main sewer lining work, to prevent odors in your home, please pour two to three cups of water into each basement floor drain. Please restrict your water usage as much as possible.
This project is expected to be completed by March 4, 2027.
Any damages in the area as a result of the sewer lining work will be restored to its pre-lining state. However, the Department of Water Management does not assume responsibility for damage to privately installed parkway improvements, including sprinkling systems, fences, flower beds and shrubbery. Sewer lining is not complete until damaged sidewalks, parkways and streets have been repaired.
Should you have any questions of concerns, you can either ask the construction foreman during the project, the engineer on site or call any of the following numbers:
-
24-Hour Service an Information line: 311
-
DWM Office of Public Affairs: (312) 744-6635
Grace Street Water Main Replacement
Updated July 21, 2026
Pipe installation along Grace Street and Lawndale is complete. Restoration work is scheduled to start once the underground phase is completed, weather permitting.
The contractor is planning a shutdown on Wednesday, July 22, for the final connection at the intersection of Grace and Lawndale.
No residents are expected to be impacted by the water shutdown.
No parking signs will be placed for the duration of the work.
Parking Restrictions
-
“No Parking” signs will be posted on both sides of the street during construction hours (7:00 AM – 4:00 PM).
-
Parking will be allowed outside of work hours and on weekends.
Traffic and Lane Closures
-
Local traffic may be limited during work hours due to staging of trucking and the movements of other machinery needed to perform the work.
-
One lane will always remain accessible for emergency vehicles.
Water Shutdowns
-
There is no water shutdown planned for this week.
Water Service Transfers / Lead Service Line Replacement (LSLR)
-
Lead service line replacements will begin once the water main installation is complete.
Final Connections and Restoration
-
After all buildings are connected to the new water main, final connections will be made to fully remove the old water main from service.
-
Restoration will follow shortly after.
Austin-Marmora Sewer Project
Updated November 6, 2026
The Department of Water Management (DWM) has issued work orders to rehabilitate the following existing sewer sections within the 30th Ward:
-
N Austin Ave from W Diversey Ave to 335’ North of W George St
-
N Marmora Ave from W Diversey Ave to W George St.
Traffic control: N Marmora Ave will be closed to through traffic from W Diversey Ave to W George St during work hours. Parking signs have been posted.
Status: In-Progress
-
DWM in-house main lead service line replacement (LSLR) in progress on N Marmora Ave (30 services): Main line sewer and catch basins completed.
-
LSLR in progress, with 14 of 30 addresses worked so far.
-
Public and private complete (6): 2819, 2820, 2827, 2832, 2836, 2850
-
Public side complete, private side pending homeowner (4): 2814, 2815, 2818, 2824
-
Private side complete, public side open (1): 2833
-
Completed this week: 2832: private side (now fully complete), 2821: public side only, 2833: private side only, 2838: public side only
-
Remaining: 16 addresses not yet started
-
Sewer System Maintenance
Updated June 26, 2026
The Department of Water Management has issued work orders to rehabilitate the following existing sewer sections within the 30th Ward:
-
N Avondale Ave from 238' Southeast of N Hamlin Ave to W Addison St
-
N Kildare Ave from W Cornelia Ave to W Henderson St
-
N Mcvicker Ave from W Wellington Ave to 330' North of W George St
-
N Mcvicker Ave from W George St to W Wrightwood Ave
-
N Kostner Ave from Alley South of W Roscoe St to 3 Sections (380') N of W School St
-
W Cornelia Ave from N Karlov Ave to Alley (160') West of N Pulaski Rd
The Notice to Proceed is June 30, 2026, and the sub-contractor, Inliner Solutions, will have 175 calendar days to complete all work on the subject Sub Order 22a. The completion date will be December 22, 2026.
The rehabilitation work includes cleaning the sewers and the installation of CIPP (cure-in-place pipe). The installation of CIPP consists of lining the existing sewers and generally does not require excavation except when repairs are required prior to lining of the sewer main, catch basin lateral connections, catch basin structures or manhole structures.
Typical work includes the following:
-
Main sewer cleaning and televising
-
Catch basin (drainage structures on the curbside) cleaning, televising, and lining of the pipe connections to the main sewer
-
Catch basin and sewer manhole structures lining
-
Main sewer lining immediately followed by the reinstatement of house drains services and catch basin pipe connections.
-
The lined sewer will be televised to ensure that the work was done properly.
The work is scheduled to begin TBD and is scheduled to be completed by TBD.
Please note, the work is performed in staggered stages, therefore crews will not be on site every day for the extended period described. As contractors begin lining the main sewers, residents will be provided with a letter/flyer with notification of the work for each project location. No parking signs will be posted in the immediate area a workday prior to the start of any scheduled work. It will be necessary to close some lanes, but the streets will remain open to traffic.